Meeting Minutes 10/17/2013

Trapper Creek Community Council
Official Meeting Minutes October 17, 2013

Meeting called to order 6:30 pm.
Board Members in Attendance: Miller, Glenka, Kolbeck, Leo. Community members in attendance: Lon McCullough, Juliah DeLoach & Mike, Jeff & Janet Grelson, Tom Daniels, George & Kaye Faerber, Earl Theroux, Rick Ernst, Gary or Greg, James Stanley, Debbie Garrett, Klaus Lerch, Donna Massey, Jennie Earles, Craig Cebula, Mr. & Mrs. Boone. Teleconference Molly Duren. Assemblyman Vern Halter, RSA Joan Medberry, and RSA Mike Lachelt.
Reading and approval of minutes from September meeting.
Assembly Report
? TCCSA CIP Report: Gravel delivered and spread out. Sonotubes set, building being prepared for being set in place. First CIP spent. Second coming.
RSA 30 Report: Nothing new to report.
Treasurer?s Report: Checking $966.20 & Savings: $25.18
Revenue Sharing Project Updates:
FY2010
? Playground Equipment ? Playground designed and parts to finish have been ordered from Moore?s Hardware. On hold until spring.
FY2012
? Oral History ? 28 transcripts done.
? TC Park Operating Costs – $700 remaining.
? Artist in School Program ? No funds spent.
? Council Administrative Funds ? $731.64 remaining.
Current Mail: Read
Public Forum: None
Unfinished Business:
? RSA 30 board wants TCCC support for paving the first 6 miles of Oilwell Road. Public comment was taken. Leo made motion to support RSA 30 Resolution to pave first 6 miles of Oilwell Road. Yes: Glenka and Kolbeck. No: Miller
New Business: TCCC seeking candidates to fill three board seats. Applications available at TC Post Office and Library as of October 21st. Application deadline is November 21, 2013. Voting is December 2nd through 7th, during library hours. TCCC elections will be held at December 19 meeting. Board positions to take seat January 16, 2014.
Date of next meeting scheduled for November 21, 2013 at 6:30 pm.
Meeting adjourned at 8:58 pm

(Minutes taken by Council Secretary, Levi Miller)

Approved: ____________________________ _____________________________
Chairperson Date Secretary Date

Meeting Minutes 9/19/2013

Trapper Creek Community Council
Meeting Minutes September 19, 2013

Meeting called to order 6:30 pm.
Board Members in Attendance: Miller, Glenka, Kolbeck, Leo. Community members in attendance: Lon McCullough, Juliah DeLoach, Phillip Moore, and Jeff & Janet Grelson. Assemblyman Vern Halter, RSA 30 board member Joan Medberry, and DF&G David Holin.
Reading and approval of minutes from August meeting.
Assembly Report:
? TCCSA CIP Report ? Modular building project progressing slowly.
Treasurer?s Report: Checking: $966.16 & Savings: $25.17 = $991.33
Revenue Sharing Project Updates:
FY2010:
? Free Box ? Complete, all funds spent.
? Playground Equipment ? Borough has donated equipment we are waiting to pick it up.
FY2012:
? Oral History – $951 remaining.
? TC Park Operating Costs – $800 remaining for labor.
? Artist in School Program ? Project to begin May 5th.
? Council Administrative Funds ? $731.64 remaining.
Current Mail – Read
Public Forum:
? TC Blue Grass: Phillip Moore addressed concerns seeing as his family owns adjacent property.
? David Holin, DF&G Subsistence Survey: Presentation of preliminary report provided, with a follow-up copy to be mailed for council review.
? Oilwell Road paving to mile 6: RSA 30 wants money from Roads to Resources (RTR) program to pave the first 6 miles of Oilwell Road. They are requesting support of the TCCC for this project.
Unfinished Business: None
New Business: None
Date of next meeting scheduled for October 17, 2013 at 6:30 pm.
Meeting adjourned at 9:10 pm

(Minutes taken by Council Secretary, Levi Miller)

Approved: ____________________________ _____________________________
Chairperson Date Secretary Date

Meeting Minutes 8/15/2013

Trapper Creek Community Council
Meeting Minutes August 15, 2013

Meeting called to order 6:30 pm.
Board Members in Attendance: Leo, Kolbeck, Glenka, Miller
Reading and Approval of Minutes
Assembly Report: None
TCCSA Report: Modular building construction bids received
Treasurer?s Report: Checking $1,178.12 & Savings: $25.17
Revenue Sharing Project Updates:
FY2010
? Playground ? Equipment being purchased, funds not yet disbursed
? Free Box ? Remaining funds $1,030.98
? TCCC Operating Costs ? No reaming funds, project complete
FY2011 & 2012
? Oral History ? Remaining funds $951.81
? TCCSA Operating Costs ? Remaining funds $800
? Welcome Sign North ? Project complete
? Artist in School ? No activity
? YCC Vehicle Maintenance ? No remaining funds, project complete
? TCCC Operating ? Remaining funds $943.74
Current Mail: Read
Public Forum
? In lieu of speed reduction through Trapper Creek, DOTPF wants flashing beakers at Parks Highway intersecting with Susitna & Petersville Roads. Flashing yellow on highway; flashing red on intersecting roads.
? DOTPF introduces Aaron Hughes, Project Manager, Petersville Road Preventative Maintenance ? Under current prescription, the wide shoulder will not be paved. Safety issue does not allow for any additional shoulder/ pavement than what currently exists.
Unfinished Business:
New Business: None
Date of next meeting scheduled for August 15, 2013 at 6:30 pm.
Meeting adjourned at 7:40 pm

(Minutes taken by Council Secretary, Levi Miller)

Approved: ____________________________ _____________________________
Chairperson Date Secretary Date

Meeting Minutes 7/18/2013

Trapper Creek Community Council
Meeting Minutes July 18, 2013

Meeting called to order 6:30 pm.
Board Members in Attendance: Glenka, Kolbeck, Leo. Community members in attendance: Lon McCullough, Jennie Earles, Rick and Kathy Ernst, Kristie Parsons, Vern Halter, and Jon Knowles from DOT.
Minutes from June meeting were not available.
Assembly Report:
? TCCSA CIP Report ? New grant finalized and a purchase order is in place for the new monies. Bid proposal for moving new building accepted and work to commence August 1.
Treasurer?s Report: Checking: $1,178.12 & Savings: $25.17 = $1,203.29
Revenue Sharing Project Updates:
FY2010:
? Playground Equipment – Project pending. $1,500 remaining.
? Free Box ? Expenditures totaling $3162.07, June 21 through July 16.
? Council Administrative Funds ? Fully expended June 30.
FY2011-2012:
? Utility Tractor – Project was completed in June 2013.
? Oral History – Project has started, but no expenditures yet.
? TC Park Operating Costs – Expenditures totaling $ 220 since June 20.
? Welcome Sign North ? The north facing Trapper Creek Sign is complete.
? Artist in School Program – Funded $2,000. To date no funds have been used.
? YCC Vehicle Maintenance – Funded $481.84. To date no funds have been used.
? Council Administrative Funds ? Expenditures totaling $50 since July 10
Current Mail – None
Public Forum:
? Presentation on Petersville Road upgrades was given by Jon Knowles.
? Presentation by Rick Ernst re Jessica Stephens Foundation offering $10,000 in grant monies to be doled out in September. Deadline for grant application is July 26th at 9 pm.
Unfinished Business:
New Business:
? To express appreciation for the $70,000 appropriated to Trapper Creek Community Services for Park building improvements, Leo to write letter and email Eric Phillips at eric.phillips@matsugov.us. A card in the mail to follow.
Date of next meeting scheduled for August 15, 2013 at 6:30 pm.
Meeting adjourned at 7:30 pm

(Minutes taken by Council Treasurer, Paula Glenka)

Approved: __________________________ ___________________________________
Chairperson Secretary

Meeting Minutes 6/20/2013

Trapper Creek Community Council
Meeting Minutes June 20, 2013

Meeting called to order 6:30 pm.
Board Members in Attendance: Leo, Kolbeck, Glenka, Miller
Reading and Approval of Minutes
Assembly Report: None
TCCSA Report: Modular building awaiting construction bids
Treasurer?s Report: Checking $1,241.01 & Savings: $25.16
Revenue Sharing Project Updates:
FY2010
? Playground ? Equipment being purchased
? Free Box ? Building materials purchased
? TCCC Operating Costs ? Remaining funds are $7
FY2011 & 2012
? Tractor ? No remaining funds
? Oral History ? Project started
? TCCSA Operating Costs ? Prepaid most of the annual operating overhead costs
? Welcome Sign North ? Under construction, erect this Friday
? Artist in School ? No funds spent
? YCC Vehicle Maintenance ? No funds spent
? TCCC Operating ? No funds spent
Current Mail: None
Public Forum
? In lieu of speed reduction through Trapper Creek, DOTPF wants flashing beakers at Parks Highway intersecting with Susitna & Petersville Roads. Flashing yellow on highway; flashing red on intersecting roads.
? DOTPF update on Petersville Road project ? hope to get funding this winter and start in spring 2014. Petersville Road from pavement break to Kroto will be resurfaced (gravel) this summer 2013.
Unfinished Business:
New Business: None
Date of next meeting scheduled for July 18, 2013 at 6:30 pm.
Meeting adjourned at 7:10 pm

(Minutes taken by Council Secretary, Levi Miller)

Approved: ____________________________ _____________________________
Chairperson Date Secretary Date